  1. Nov 12, 2026 9:06 AM GMT (1 week ago) · Investigating

    National Grid have restored mains power.
    Site no longer at risk.

  2. Nov 11, 2026 12:15 PM GMT (1 week ago) · Investigating

    Leominster cabinet currently on battery power.
    Engineer to attend site this afternoon to investigate.

Impacted:
FullFibre Network

Planned Works - A57 Diversion works Hyde - Glossop

A third-party contractor will be carrying out planned works to re-route fibre cables ahead of construction of the new Hyde - Glossop bypass.

When: Over 4 nights, from 30/11/26 to 03/12/26, between 00:00 and 06:00 each night.

Impact: Services should be treated as at risk throughout the 00:00–06:00 window on each night. Affected customers should expect a loss of service of around 1 hour while the fibre is spliced. Services will be restored automatically once each night’s work is complete.

What do I need to do?

Please do not switch off your equipment during this time.
If you have trouble getting back online after 06:00, simply restart your Hub.

We apologise for any inconvenience and thank you for your patience while these works are carried out.

Scheduled for Nov 20, 2026 3:18 PM GMT - Dec 3, 2026 6:00 AM GMT

View all updates
  1. Nov 20, 2026 3:21 PM GMT (4 days ago) · Scheduled

    A third-party contractor will be carrying out planned works to re-route fibre cables ahead of construction of the new Hyde - Glossop bypass.

    When: Over 4 nights, from 30/11/26 to 03/12/26, between 00:00 and 06:00 each night.

    Impact: Services should be treated as at risk throughout the 00:00–06:00 window on each night. Affected customers should expect a loss of service of around 1 hour while the fibre is spliced. Services will be restored automatically once each night’s work is complete.

    What do I need to do?

    Please do not switch off your equipment during this time.
    If you have trouble getting back online after 06:00, simply restart your Hub.

    We apologise for any inconvenience and thank you for your patience while these works are carried out.

Impacted:
Network - Hyde
Scheduled maintenance
Published Oct 28, 2026 12:20 PM GMT

Planned Works - Cannock & Dodworth

Scheduled for Nov 30, 2026 12:01 AM GMT - Nov 30, 2026 6:00 AM GMT

We're carrying out essential maintenance on our network to keep your broadband running smoothly. This means a service interruption in the early hours of 30 November 2026 while we upgrade key equipment in your area.

When: 30 November 2026
Time: Between 00:01 - 06:00
Expected downtime: 15 Minutes

What do I need to do?

Please do not switch off your equipment during this time.
If you have trouble getting back online after 06:00, simply restart your Hub.
Thanks for your patience while we make these improvements!

Scheduled maintenance
Published Nov 17, 2026 2:15 PM GMT

Planned Network Upgrades: Altringham, Cleveleys & Skelmersdale

Scheduled for Dec 1, 2026 12:01 AM GMT - Dec 1, 2026 4:00 AM GMT

We're carrying out essential maintenance on our network to keep your broadband running smoothly. This means a service interruption in the early hours of 1 December 2026 while we upgrade key equipment in your area.

When: 1 December 2026
Time: Between 00:01 - 04:00
Expected downtime: 15 Minutes

What do I need to do?

Please do not switch off your equipment during this time.
If you have trouble getting back online after 06:00, simply restart your Hub.
Thanks for your patience while we make these improvements!

Scheduled maintenance
Published Oct 28, 2026 12:24 PM GMT

Planned Works - Crewe, Winsford & Northwich

Scheduled for Dec 1, 2026 12:01 AM GMT - Dec 1, 2026 6:00 AM GMT

We're carrying out essential maintenance on our network to keep your broadband running smoothly. This means a service interruption in the early hours of 01 December 2026 while we upgrade key equipment in your area.

When: 01 December 2026
Time: Between 00:01 - 06:00
Expected downtime: 15 Minutes

What do I need to do?

Please do not switch off your equipment during this time.
If you have trouble getting back online after 06:00, simply restart your Hub.
Thanks for your patience while we make these improvements!

Scheduled maintenance
Published Nov 17, 2026 2:22 PM GMT

ACX Planned Network Upgrades - Nationwide

Scheduled for Dec 1, 2026 12:01 AM GMT - Dec 1, 2026 4:00 AM GMT

We're carrying out essential maintenance on our network to keep your broadband running smoothly. This means a service interruption in the early hours of 1 December 2026 while we upgrade key equipment in your area.

When: 1 December 2026
Time: Between 00:01 - 04:00
Expected downtime: 30 Minutes

What do I need to do?

Please do not switch off your equipment during this time.
If you have trouble getting back online after 06:00, simply restart your Hub.
Thanks for your patience while we make these improvements!

Scheduled maintenance
Published Oct 28, 2026 12:28 PM GMT

Planned Works - Congleton, Northallerton, Richmond, Wombourne, Sandbach & Penistone.

Scheduled for Dec 2, 2026 12:01 AM GMT - Dec 2, 2026 6:00 AM GMT

We're carrying out essential maintenance on our network to keep your broadband running smoothly. This means a service interruption in the early hours of 02 December 2026 while we upgrade key equipment in your area.

When: 02 December 2026
Time: Between 00:01 - 06:00
Expected downtime: 15 Minutes

What do I need to do?

Please do not switch off your equipment during this time.
If you have trouble getting back online after 06:00, simply restart your Hub.
Thanks for your patience while we make these improvements!

Scheduled maintenance
Published Nov 17, 2026 2:24 PM GMT

ACX Planned Network Upgrades - Nationwide

Scheduled for Dec 2, 2026 12:01 AM GMT - Dec 2, 2026 4:00 AM GMT

We're carrying out essential maintenance on our network to keep your broadband running smoothly. This means a service interruption in the early hours of 1 December 2026 while we upgrade key equipment in your area.

When: 1 December 2026
Time: Between 00:01 - 04:00
Expected downtime: 30 Minutes

What do I need to do?

Please do not switch off your equipment during this time.
If you have trouble getting back online after 06:00, simply restart your Hub.
Thanks for your patience while we make these improvements!

Scheduled maintenance
Published Oct 28, 2026 12:37 PM GMT

Planned Works - Chapeltown, Codsall, Easingwold, Great Ayton, South Elmsall, Sherburn, Stokesley, Middlewich & Tadcaster

Scheduled for Dec 3, 2026 12:01 AM GMT - Dec 3, 2026 6:00 AM GMT

We're carrying out essential maintenance on our network to keep your broadband running smoothly. This means a service interruption in the early hours of 03 December 2026 while we upgrade key equipment in your area.

When: 03 December 2026
Time: Between 00:01 - 06:00
Expected downtime: 15 Minutes

What do I need to do?

Please do not switch off your equipment during this time.
If you have trouble getting back online after 06:00, simply restart your Hub.
Thanks for your patience while we make these improvements!

System Status

Sep 2, 1540 - Oct 31, 1540

FullFibre Network

· --% uptime
Sep 2, 1540
Oct 31, 1540

Network - Alcester

· --% uptime
Sep 2, 1540
Oct 31, 1540

Network - Alfreton

· --% uptime
Sep 2, 1540
Oct 31, 1540

Network - Alrewas

· --% uptime
Sep 2, 1540
Oct 31, 1540

Network - Altrincham

· --% uptime
Sep 2, 1540
Oct 31, 1540

Network - Asfordby

· --% uptime
Sep 2, 1540
Oct 31, 1540

Network - Ashbourne

· --% uptime
Sep 2, 1540
Oct 31, 1540

Network - Askern

· --% uptime
Sep 2, 1540
Oct 31, 1540

Network - Bacup

· --% uptime
Sep 2, 1540
Oct 31, 1540

Network - Bakewell

· --% uptime
Sep 2, 1540
Oct 31, 1540
Loading components…
Incident history